Associated British Ports

Associated British Ports – Southampton, Eastern Dock Rail Improvement Works
Renewal and Remodelling of Eastern Docks Infrastructure during 19 day blockade.

Works Commenced July 2014 – Completed August 2014.
The Scope of Work Included:
  • Removal of existing ballasted track – 1200m
  • Break out and Remove track in concrete – 200m
  • Excavation and disposal of materials
  • Preparation of formation
  • Installation of track drainage
  • Installation of ballasted Track – 1350m
  • Installation of ballasted Turnouts -2 nr
  • Installation of embedded Track – 150m – Including Concrete Pour
  • Installation of Proprietary Crossing – 2 nr