P-Way renewal – Network Rail infrastructure

Selby Swing Bridge P-Way Renewals -Bridge and Approach Tracks:

Project Start Date: 26th July 2014 – Completion Date: 7th September 2014 (6 week Blockade).
The Scope of Work Included:
  • 1stinrail were responsible for the track removal to facilitate the upgrade of the
    bridge deck and rail bearers as part of a major upgrade of the entire structure
  • 1stinrail were responsible for the installation of VIPA baseplates throughout the bridge
    area. Including materials provision, engineering, track installation, tamping, stressing,
    Track Handback, and track monitoring.
  • All works were undertaken during a blockade and involved careful planning and
    flexible working to facilitate all other contractors involved in this project and at the
    same time ensuring no delays to handback for traffic upon completion.